Australia’s data-centre electricity use is expected to climb from 3% of national supply to about 13% by 2035. Governments and investors are weighing AI infrastructure’s power demands against energy supply and community concerns. Last month, state premiers and chief ministers agreed on standards requiring operators to bring forward new renewable power to offset demand. Queensland secured an exception allowing some gas use where it wouldn’t raise household bills.
The question isn’t just where computing facilities get electricity. At a roundtable on AI infrastructure, participants also described domestic data centres as a way to retain sensitive data, skills and economic gains in Australia instead of relying on overseas infrastructure.
Power, policy and communities
Australia has about 165 data centres operating, with another 225 in development. A separate New South Wales plan would require data centres to source at least 40% of their electricity from wind. The national standards and state plan put energy requirements at the centre of decisions about where facilities can be built and how quickly they can operate.
NAB executive, specialised finance, sustainability &innovation Jacqueline Fox said growth brings “substantial economic opportunities,” but must be balanced against “legitimate community concerns, including around energy.” Communities, she said, need to “understand, trust and share in those benefits.”
Operators warned that renewable generation and data-centre construction don’t run on the same timetable. A data centre might be delivered in two years, while a large utility-scale renewable project could take more than four years and have a 20-year payback. A large solar farm typically takes three to four years, around 41 months, from initiation through commissioning; a large onshore wind farm typically takes more than six years.
AirTrunk vice-president and group treasurer Luke Stephens said, “At the moment, the community expects that if you're building a big data centre, you've got green electrons day zero.” New renewable generation, firming and transmission can’t always arrive on the same timeframe as a new facility, he said. Rob Bartrop urged governments to take a “softly-softly” approach to renewable mandates, saying requirements framed around 18- or 36-month periods might be impossible to meet immediately.
Who controls the infrastructure
CDC chief strategy officer Dr Jack Dan said local data centres could reduce reliance on overseas infrastructure. AirTrunk associate vice-president for social impact and community Rob Bartrop said domestic infrastructure could help Australia retain sensitive data, skills and AI-related economic and productivity gains. Australians would use cloud and AI services wherever the infrastructure was located, he said, making domestic hosting strategically sensible.
That prospect depends on having power where customers need it. NEXTDC group treasurer Mark Bower said energy projects ideally needed to come online within about two years to match data-centre development. “These deployments are mobile,” Bower said. “They will pass Australia by if we cannot meet the demand timing of data centre customers.” AirTrunk vice-president and group treasurer Luke Stephens said hyperscalers were considering other regional hubs.
Participants said Australia’s political stability, institutions, capital markets, experienced operators, renewable resources and proximity to Asian economies offered advantages. Energy and grid capacity remain challenges. McKinsey estimates technology companies will invest $US7 trillion in data centres by 2030.
Capital, jobs and the energy gap
AirTrunk secured a A$4.25 billion ($3 billion) green loan to finance development of a Sydney data-centre campus. The project will add infrastructure for cloud, AI and other digital services used by Australian businesses, governments and communities. It’s expected to support more than 10,000 jobs across construction, trades, engineering, logistics and safety.
Banks alone would be stretched by the scale of investment, said Archit Goradia, NAB executive director, sector lead – technology. NAB was working to ensure “deep and functioning capital markets” could deploy capital at scale, he said. Participants also warned investors to distinguish operators with real customers, long contracts, development capability and secure power from speculative proposals based on AI enthusiasm.
Bartrop said an illustrative 5 gigawatts of data-centre demand in 10 years could require 10 to 15 gigawatts of renewable generation. Planners, he said, must decide where computing capacity and power should be located, and whether they should be co-located or connected by transmission and fibre. Tilt Renewables chief executive Anthony Fowler said a foundation contract with a data-centre operator could help unlock the proposed 1.2-gigawatt Nonowie wind project near Whyalla.
Participants said coordination could make data centres foundation customers for new generation, while supporting electrification and replacement of retiring coal-fired power. Without sufficient power and investment, they said, jobs and strategic control could remain offshore.