Published on
Saturday, October 10, 2026 at 12:10 PM

By Marcus Okonkwo — Far-Left Desk

Private Contractor, Ministry Blamed for Mauritania Outages

An independent commission held a private company and officials at Mauritania’s Energy Ministry responsible for fires that cut electricity to large areas of Nouakchott and nearby towns. Hours after the prime minister resigned over the report, President Mohamed Ould Cheikh El Ghazouani reappointed Mohamed Ould Cheikh and tasked him with forming a new government.

Who Was Held Responsible

The commission identified “serious shortcomings regarding prevention, electrical protection, work supervision, and emergency management.” Its report said electrical connectors that failed to meet required technical standards caused the fires, and that a private company had imported them.

Three newly installed electrical power lines figured in the commission’s account. It identified overheating as the most likely cause, rather than sabotage or operational error. The commission held the company and Energy Ministry officials responsible for the incidents.

The article names neither the private company nor the officials held responsible. It gives no financial figures for the company, the connectors, or the damage caused by the outages. The commission’s reported findings identify a private supplier and ministry officials, but don't describe penalties or other action against them.

Who Bore the Outages

The fires broke out less than 24 hours apart, on 21 and 22 August, at transformer substations belonging to the Mauritanian Electricity Company, known as Somelec. The substations serve Nouakchott and its suburbs.

The resulting outages affected large areas of the capital and the towns of Ouad Naga, Idini and Aouleigat. They lasted three to five days. The article doesn't give the number of people affected, identify particular households or businesses, or describe material losses caused by the outages.

The commission tied the failures to connectors that did not meet technical standards and to problems in prevention, protection, supervision and emergency management. It identifies imported equipment and oversight failures, but doesn't state who selected the connectors or explain how officials approved them for use.

The Government’s Response

The prime minister resigned over the report into the fires. On Friday, President Mohamed Ould Cheikh El Ghazouani met with Mohamed Ould Cheikh and tasked him with forming a new government. The president acted hours after the resignation.

The reported commission findings assign responsibility to a private company and Energy Ministry officials. The article provides no details of proposed reforms, compensation, or changes to the ministry’s oversight. It also doesn't report comments from residents affected by the outages, workers, unions or other organized groups, and contains no account of labor action.

The article doesn't report company profits, contracts or the cost of the imported connectors. It provides no further detail about the new government’s composition or its response to the commission’s findings. The sequence is clear: power failures, an investigation assigning responsibility, a resignation, and the prime minister’s reappointment hours later.

Reviewed by the editorial desk — October 10, 2026
Last updated October 10, 2026
← Back to articles