Federal environmental approvals in Queensland take an average of 1,150 days and can cost up to $7.7 billion a year, according to figures cited by Queensland Treasurer David Janetzki. Those figures predate the 2025 reforms, and the Queensland Productivity Commission says it can’t yet assess the changes fully because several remain unfinished. Its final review will be delivered in July next year, three months later than planned.
The delay leaves Queensland without a complete assessment of how Canberra’s environmental law overhaul affects the state’s infrastructure pipeline. The commission’s interim report said some reforms had not been drafted, shared for consultation or implemented, leaving “limited observable evidence on the impacts of the reforms in their entirety.” It said a complete assessment “may not be achievable for several years.”
Rules Without a Full Assessment
The Commonwealth passed the overhauls late last year, after federal environmental laws had remained largely unchanged for more than 20 years. The reforms aimed to cut approval times for major projects while setting clear environmental standards and safeguards. A years-long stalemate in Canberra had delayed their passage.
Queensland raised concerns about the changes and in April tasked its Productivity Commission with examining their effect on the state’s infrastructure pipeline. The commission’s review is intended to give the state a basis for assessing the reforms, but the absence of completed measures limits what it can conclude now.
The interim report identified deficiencies in the continuing reforms. Some elements lacked consultation and resulted in greater costs for agriculture, the commission said. New land-clearing requirements effectively extended regulation to small and family farming businesses, according to its findings.
The commission estimated those requirements could cost Queensland’s agriculture industry between $14 million and $41 million a year. It also warned of unintended consequences for routine land management and some environmental outcomes.
Queensland and Canberra Clash
Janetzki said the changes introduced by Canberra were “adding cost and delay.” He called the commission’s report “startling” and cited the approval-time and cost figures, while his office said establishing a baseline for comparison was important because the figures predated implementation of the 2025 reforms.
Janetzki denied the final report had been delayed, describing the schedule change as an extension. He said the inquiry was meant to put Queensland in the best position to negotiate with the federal government.
“Anything that improves productivity in Queensland is an important investment, and the Productivity Commission, through all those inquiries and reporting that they are doing, is helping arm the government with productivity measures,” Janetzki said. “Queensland's doing it. The federal government isn't.”
Federal environment minister Murray Watt, a Queensland senator, called the review a “political stunt.” He said other states were about to sign agreements with the federal government “to reduce red tape and speed up project approvals.” Watt accused Queensland of choosing to “slow down projects, waiting for a do-nothing productivity report on laws that haven't even fully begun.”
“Under the Crisafulli Government, Queensland is no longer the smart state, it's the slow state,” Watt said.
Costs, Consultation and the Next Report
The 15-month inquiry’s cost wasn’t disclosed. Janetzki said it was included in the commission’s $6.7 million annual budget. Stakeholders can submit feedback on the interim report before the final assessment arrives in July next year.
Queensland’s “Smart State” slogan and trademarks were retired in 2012 under then-premier Campbell Newman's LNP government. The current dispute concerns how federal approval rules affect projects, farming businesses and the state’s ability to negotiate with Canberra. The commission says the reforms remain too incomplete for a full accounting; the competing claims from Queensland and the federal government now await a final report.