Democratic victories in Nevada, Georgia, Ohio and Texas could put 45% of planned U.S. data-center capacity under states whose leaders support expanding or extending construction moratoriums, Goldman Sachs estimates. Texas, where a governor’s race upset helped shift the political picture, is expected to host a quarter of the planned AI infrastructure buildout.
The elections put state and local officials in a position to affect projects through permits, electricity service and tax incentives. Governors-elect have proposed ending tax breaks, tightening climate and electricity restrictions, and allowing local governments to impose construction moratoriums. Wells Fargo estimates that every 10% reduction in planned Texas data-center capacity would cut Big Tech companies’ AI infrastructure spending by 1.6%.
Who Controls the Buildout
The economic stakes are large. ING economists say AI infrastructure investment has accounted for as much as a quarter of U.S. economic growth this year. Stijn Van Nieuwerburgh, a Columbia Business School economist, said annual spending on AI infrastructure is expected to approach $1 trillion for the foreseeable future. As a share of gross domestic product, he said, that would exceed every other investment boom in modern U.S. history, including railroad construction.
State and local officials can influence whether projects get financed, said Mona Dajani, co-chair of Cooley’s infrastructure, energy and real estate practice. Hundreds of developments awaiting permits, utility service or tax incentives could be exposed to policy changes. Projects already under construction could face risks, too.
Texas law grandfathers in permits for some projects, protecting them from later changes to local permitting requirements. But that protection doesn’t cover changes to state permitting or electrical-service guarantees that Governor-elect Gina Hinojosa could vacate. Delayed approvals can add costs as interest, equipment commitments and utility expenses continue to accrue, Dajani said. Some existing projects could eventually become financially unviable.
Investment Risk and Public Opposition
The scale of planned construction exceeds what is already underway. The United States had 5,427 data centers at the end of last year, according to Stanford University’s AI Index Report. AI companies have announced plans for 3,969 new U.S. data centers, according to data-center research company Aterio, but only about 800 are under construction. AI experts have questioned whether many announced projects are viable.
Financial pressure is already visible in parts of the industry. CoreWeave, a neocloud business that rents computing capacity, recently projected extensive losses, and its bond yields surged to 15%. Its expected return on investment was about 9%. Amazon, Google, Meta and Microsoft have deeper pockets, but their stocks have fallen in recent weeks as investors questioned spending that may not generate profits for years.
Public opposition has included a protest against data-center expansion at the Texas Capitol before a Texas Senate Committee on Finance hearing on July 27, 2026, and a protest against data-center development outside the Austin Marriott Downtown on September 2, 2026. The article reports bipartisan support for guardrails. Texas Republican Governor Greg Abbott had already imposed a data-center moratorium, and Hinojosa campaigned on extending it until lawmakers establish stronger AI regulations.
The Limits of the Investment Case
Donald Trump has opposed efforts to curb AI growth and spending, citing economic and national security concerns, especially competition with China. Many Republican politicians who might otherwise have backed AI regulations, including rules for data-center construction, remained silent.
A slowdown could reduce growth and give companies more time to plan. Joe Brusuelas, chief economist at RSM US, expects growth to ease from last quarter’s 3.4% pace to closer to 2.4% if AI investment slows, while remaining solid over the long term. “It’s slowing, but it doesn’t mean we’re going to have a recession,” he said.
Mike Mathews, global digital infrastructure practice leader at risk adviser Marsh, said data centers already face $200 billion in project delays. The rushed race to build first and biggest has left money sunk in projects that don’t work, the article said. In the previous decade, Google and other companies promoted sustainable construction using renewable energy during the cloud-computing expansion. Harry Krejsa, director of studies at the Carnegie Mellon Institute for Strategy & Technology, said a company that squanders its political license to operate at home could face a greater obstacle to competing with China.